Beton entreprenør
Rørvig Byg were the subcontractor assigned by Lind & Risør on our house project. They have made very big and obvious mistakes when pouring concrete for foundation of 2 of the house pillars. For example they have used styrofoam foam as framework around a pillar foundation instead of proper wood when pouring concrete, and it resulted in a mess when styrofoam framework was cracked open. (A proper redo of the work had to be done by Lind & Risør).