Over Promised, Under Delivered, Never Completed
Our contract was for a unit to be delivered complete on our section within 13 weeks of starting, which means the unit should have been completed in September last year (2021). The unit was delivered incomplete and with substantial defects on 11 January 2022, 4 months late. It has now been more than a year since the unit should have been completed. We attempted to contact the company for several months with no success, including after we got our legal counsel involved. Not until we posted a poor review online did we hear anything. They turned out to be just more empty promises.
In addition Podular subcontracted our personal builder to fix the issues with the unit after it was delivered, but he has still not been paid for any of the work he has done since before 1 June this year (2022). Our builder tells us he has contacted the other engineers you subcontracted, who say they are also waiting for their invoices to be paid.
Rotorua-Lakes Council has also confirmed that it is waiting for payment before it will issue Code Compliance Certification. Per our contract, you should have obtained Code Compliance before the unit was delivered to our site in unfinished condition.
After becoming incredibly frustrated at the lack of progress and lack of communication with us we have finally had to CANCEL our contract with Podular, take our losses, pay Rotorua council ourselves and finish the unit on our own.
We have been contacted by several other of your customers who claim they are in the same or worse situation than us. After posting a negative review on your social media, you deleted it so others would not find out and then blocked us. I find that truly deceptive for the general public.
We negotiated in good faith, gave you ample time to resolve issues but now feel very cheated!